Description:
You are currently running CA Workload Automation EE Master, Proxy, Shadow and Workstation Server STC. What's the correct order in which to start them after IPL?
Solution:
Here is the recommended order:
- Tracking CA Workload Autoamtion EE system (like proxies) should be started first to avoid any loss of tracking data.
- Master should be started BEFORE Shadow; otherwise Shadow will act as Master.
- Workstation Server STC should be started AFTER related CA Workload Automation EE system is up, otherwise it will end.