CA JOBTRAC JM r11 Procedure to Delete/Purge an event from the schedule when DELETE/PURGE commands fail
search cancel

CA JOBTRAC JM r11 Procedure to Delete/Purge an event from the schedule when DELETE/PURGE commands fail

book

Article ID: 51547

calendar_today

Updated On:

Products

Jobtrac

Issue/Introduction

Procedure to remove an event that is stuck with status (IN PROGRESS, EXECUTING, AWAIT-EXEC or ABENDED=SYS).

 

Environment

Release:
Component: JOBTRC

Resolution

The following procedure can be used for events that are stuck with status (IN PROGRESS, EXECUTING, AWAIT-EXEC or ABENDED=SYS).

  1. Select the job with a '@' to recycle status.
  2. Select the job with a 'P' to purge it (this may need to be done twice).