Description:

This behavior is working as designed when launching the project from Clarity to MSP:

  • A task with no Actuals or ETC and 0% completed: It will set duration to 0 days.

  • A task with no Actuals or ETC and 100% completed: It will set duration with the right amount of days.

Solution:

  1. Go to the Task Object--> Views--> Task Properties--> Layout Edit.

    <Please see attached file for image>

    Figure 1

  2. Go to the General Section.

    <Please see attached file for image>

    Figure 2

  3. Select the available field Fixed Duration and add it as selected.

    <Please see attached file for image>

    Figure 3

  4. Go to the Task Object--> Attributes and select the Fixed Duration attribute and click the Default option.

    <Please see attached file for image>

    Figure 4

  5. Submit it.

If "Fixed Duration" is set to 'yes', it will keep the duration shown in Clarity UI when launching the project to MSP.

<Please see attached file for image>

Figure 5

Keywords: CLARITYKB, microsoft project, scheduler, scheduling

Environment

Release:
Component: PROJECTS

Attachments

1558711576071000051545_sktwi1f5rjvs16sai.gif get_app
1558711574241000051545_sktwi1f5rjvs16sah.gif get_app
1558711572356000051545_sktwi1f5rjvs16sag.gif get_app
1558711570562000051545_sktwi1f5rjvs16saf.gif get_app
1558711568765000051545_sktwi1f5rjvs16sae.gif get_app