Issue:
When you go to the Project Properties tag, then click the "Schedule" link under the Properties section, this brings up schedule related information. There is a section labeled Staffing which has a field labeled "Default Staff OBS Unit". This field can be set to a specific OBS unit. Default Staff OBS Unit is present in Project -> Schedule page. This field is not present by default on any of the NPIO's. Staff OBS Unit is present in Staffed Resource Properties page. And this field is there for Project and NPIO's as well.
When this OBS unit is set and you export the project using XOG, the output xml file doesn't contain anything pointing to the specific OBS unit.
Steps to Reproduce:
Expected Result: Default Staff OBS Field to be exported to the XOG output.xml
Actual Result: Default Staff OBS Field won't export, no entries in output.xml
Release: ESPCLA99000-12.1-Clarity-Extended Support Plus
Component:
The issue has been reported as CLRT-47939
This is resolved in CA PPM 12.1.1