Issue/Introduction

Description:

Sometimes I see more links or options in the 'More >>' button sub-menu.

These are the two options that sometimes show or do not show on a Project > Team Detail, 'More >>' button sub-menu
       Assignment Roles
       Estimate from Allocation

Solution:

Assignment Roles:
This option appears once a Role is assigned to a task.

Estimate from Allocation:
This option is only available when an Effort Task is added to the Project. The Effort Task must have a Task ID = '~rmw'.