Description:
The PMO Accelerator Project Storyboard Report shows a different value for the Remaining Allocations than what is shown on the Project Team Detail Allocations.
We have checked our Time Slice Definitions and they cover the entire date range of the project.
Steps to Reproduce:
Expected Result: Remaining Allocations on the report should match the values on the Project Team Details portlet.
Actual Result: Remaining Allocations on the report do not match the values on the Project Team Details portlet.
Solution:
WORKAROUND:
None. Use the values shown on the Project Team Details Allocations portlet.
STATUS/RESOLUTION:
This issue is only applicable to PMO 2.x
The Project Storyboard Report was re-written for PMO 3.0 and is available now in the CA Clarity Solution Pack (CSP)
Discontinue the use of the old report definition and use the new report definition id = CSP_PRJ_ProjectStoryboard
Keywords: CLARITYKB, PMO-621, pmo20, pmo21, pmo211, pmo22, report content.