Description:
When we add the % Complete field to either the Task List or WBS (Work Breakdown Structure) the values are rounding to either 0,00 or 100,00.
If the tasks % complete is 0 to 49%, then on the view you see 0,00.
If the tasks % complete is 50 to 100%, then you see 100,00.
This can happen on non English installations.
Solution:
Log into the CSA (Clarity System Admin) program
Click on your server name
Click on the Application link
In the Application Instance: app enter the following in the Java VM Parameters field at the end: -Duser.country=US -Duser.language=en
Save your change
Stop and restart the clarity app service
This change is a low impact change.