Description:
We are updating existing projects to replace inactive Project Managers with an active Project Manager. We have activated audit trail for the Project Manager field. The audit record shown on the Project > Audit tab shows a blank Old Value for the inactive resource.
Setup Audit Trail:
<Please see attached file for image>
Steps to Reproduce:
<Please see attached file for image>
<Please see attached file for image>
<Please see attached file for image>
<Please see attached file for image>
<Please see attached file for image>
Expected Results: Old Value = Resource1
Actual Results: Old Value = blank
Solution:
WORKAROUND:
Reactivate the resource before making the change on the project. The Audit Trail will capture the Old Value correctly and the value will be seen on the Audit Trail even when the Resource is deactivated later.
STATUS/RESOLUTION:
This issue has been documented as CLRT-62886 and is assigned to development for review. If you are experiencing this problem and the workaround above does not significantly help, please contact CA Technical Support.
Keywords: CLARITYKB, CLRT-62886 clarity12open, lookup, browse_projmgr.