Description:
In the Staff Member Properties page.
If the last segment for the Soft Allocation is the same % as the Default Allocation % for the resource, and that segment does not cover the whole of the project schedule, the Booking Status can go from Hard to Mixed by just clicking on Save, without performing any changes to the page.
The questionable behavior is not that Hard Allocation segments with identical % are collapsed together; the questionable behavior is that, as a consequence, the Booking Status should changed to Mixed just because now the Hard and Soft Allocations are "equivalent" but not "identical".
Steps to Reproduce:
<Please see attached file for image>
<Please see attached file for image>
<Please see attached file for image>
Expected Result: No change to the Allocation segments, and Booking Status to remain Hard.
Actual Result: The last 2 segments in the Hard Allocation are merged [which may be acceptable] and the Booking Status is changed to Mixed [not acceptable]
Solution:
WORKAROUND:
Besides the obvious workaround of not specifying the last two segments in the Soft Allocation with the same percentage value, another workaround is to set the Start Date and Finish Date in the Staff Member Properties to explicitly cover the same period as the specified Soft Allocation segments [for the example given above, Finish Date should be set to the end of the second month].
STATUS/RESOLUTION:
This issue has been documented as CLRT-58195 and is assigned to development for review. If you are experiencing this problem and the workaround above does not significantly help, please contact CA Technical Support.
Keywords: CLARITYKB, CLRT-58195, clarity12open, projmgr.