Update Percent Complete job changes tasks marked Completed to Not Started when they have no effort and the Project Percent Complete calculation is set to Effort
search cancel

Update Percent Complete job changes tasks marked Completed to Not Started when they have no effort and the Project Percent Complete calculation is set to Effort

book

Article ID: 50223

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

In CA PPM, if % Complete Calculation method is set to Effort, the Update Percent Complete job changes task statuses from Completed to Not Started. 

Steps to Reproduce:

1. Create a project with % Complete Calculation Method set to 'Effort'.
2. Add one team member to the project
3. Create a task and assign the team member to the task
4. Go to Organizer->Tasks and change the task status to 'Completed' (which changes the % Complete to 100%)
5. Run the Update % Complete job

Expected Results: Task status remains as 'Completed', and % Complete is 100%
Actual Results: Task status changes to 'Not Started', and the % Complete changes from 100 to 0%

Environment

Release: ESPCLA99000-13.2-Clarity-Extended Support Plus
Component:

Cause

With 'Effort' % Complete Calculation method, the 'Update % Complete' job is designed to calculate the task % complete and change the status based on it.

Resolution

If a task has an assignment with no Actuals or ETC (Effort), the status will be 'Not Started' and 0% complete with % Complete Calculation of 'Effort'.

The fact that CA PPM allows you to temporarily mark the status of a task to completed by marking an assignment complete in Organizer -> Tasks is misleading to users since the status is later changed by the job. This is fixed in CA PPM 14.1 and higher as part of CLRT-74872.

Additional Information

Reference the % Complete Calculation Method section of the Create Projects, Teams, and Tasks documentation for details on the differences in the three types of % Complete Calculation Methods.