Clarity: When creating a baseline by a process, the usage field does not take into account the ETC of the subprojects
search cancel

Clarity: When creating a baseline by a process, the usage field does not take into account the ETC of the subprojects

book

Article ID: 50025

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Description:

Creating a baseline of a project with a subproject, sums the ETC of both under the usage field. When this baseline is created by a process, it only takes into account the master project's data.

Steps to Reproduce:

  1. Create a project, assign a resource and create a task (ETC 8 hours)
  2. Create a subproject, assign a resource and create a task (ETC 8 hours)
  3. Link the subproject to the master project
  4. Create a baseline through the UI. The usage field sums both ETCs to 16
  5. Now create a process to create a baseline and run it

Expected Result: To find the usage field with 16 hours
Actual Result: The usage field shows 8 hours, ignoring the subproject data

Solution:

Workaround:
On the Master Project, select the baseline and click 'Update baseline' button

Status/Resolution:
This issue has been documented as CLRT-43632 and is assigned to development for review. If you are experiencing this problem and the workaround above does not significantly help, please contact CA Support.

Keywords: CLARITYKB, CLRT-43632, clarity12open, bpm.