Clarity: Gantt Sorting Configuration

book

Article ID: 49710

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL CA Identity Manager CA Identity Governance CA Identity Portal Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Description:

Column sorting dropdowns on Projects Gantt list column layout only shows one value "WBS sort".

We cannot sort by the Start Date in the Gantt chart in Clarity 13.x - we have to manually modify the order by specific project - we want to always see the Gantt charts by the start date - there doesn't appear to be a way to configure this.

In the Gantt Portlet, Options, Configure, List Column Layout, Column Sorting - see the pull-down list of available attributes only contains 'WBS Sort'

<Please see attached file for image>

Figure 1

Solution:

This is the only value allowed for configuring the sorting on the Gantt view. The Gantt is a hierarchical view. We don't want users to sort it by anything but the sequence order. Having the ability to select any other sorting will not allow the hierarchy to function properly.

Keywords: CLARITYKB, CLRT-61783, nab, how-to, configuration.