Description:
When a project is exported to Microsoft Project (MSP), if a summary task has a milestone under it and the summary task has duration of one day it gets flipped to a milestone.
This issue affects both MSP 2007 and MSP 2010.
Steps to Reproduce:
Assumption: you have patch 12.1.1.4 and 12.1.1.4_132502_EBF.jar applied
Scenario 1:
Note: The phase is set as a milestone, and it should not be.
Scenario 2:
Note: the phase is set as a milestone, and it should not be.
Scenario 3:
Note: the activity2 and phase are now marked as milestones.
Note: the milestone information at the summary task saves back to Clarity.
Note: after saving the project back to Clarity if you uncheck the summary tasks as milestones and save to Clarity - in Clarity they still are set as milestones
Expected Result: When exporting to MSP, it should never set a summary task as a milestone
Actual Result: If the summary task has a milestone below it this may cause it to be set as a milestone
Solution:
Workaround:
None.
Status/Resolution:
Resolved in Clarity 12.1.1 Generic Patch. Reference TEC553491
Resolved in Clarity 12.1.3 Generic Patch. Reference TEC570813
Resolved in Clarity 13.1.0
Keywords: CLARITYKB, CLRT-67857, clarity12resolved, clarity1211resolved, clarity1213resolved, clarity13resolved, clarity1310resolved.