Description:
How do we set the tasks to automatically expand on the Work Breakdown Structure view when we access it?
Solution:
For a single user:
Go to the application side
Click on a project
On the Task > WBS view go to [--Actions--] > Configure
Click on Options
Select 'Automatically Expand'
Click Save and Exit
For all users:
Go to Admin Tools > Objects > Tasks
Click on Views
Click on Options for Work Breakdown Structure
Select 'Automatically Expand'
Click Save
Click Cancel
Click Publish
NOTE: Per development Auto-Expand is only intended to expand the 1st level of child rows. If we expand all levels then this would cause an unacceptable performance issue.