Description:

We have a Cost Plan set up and previously we were able to go into Edit Mode and update the Time Scale cell values. Now when we go into the Edit Mode, the application is not allowing us to edit these cells. We tried different Cost Plans and some Cost Plans allow the cells to have data entry and other Cost Plans are not allowing the user to edit the values.

Steps to Reproduce:

Clarity Version 12.x

  1. Open a Cost Plan Details page

  2. [--Actions--] Edit Mode - the 'GL Account' field is open for editing, but the TSV cells are not open

    <Please see attached file for image>

    Figure 1

Clarity Version 13.x

  1. Open a Cost Plan Details page

  2. Click into a cell in the TSV grid - the cell is highlighted, but does not open for editing

    <Please see attached file for image>

    Figure 2

Expected Result: We have the appropriate rights and we were able to update the plan previously, we should still be able to update the plan TSV values
Actual Result: The TSV fields are not open for editing

Solution:

The end-user configured the Cost Plan Details View to use 'Monthly' Time Scale Period Type and the Cost Plan Properties Period Type is set to 'Annually'.

The current behavior of the application allows only for entering data in TSV cells for Financial Plans when the Time Scale configuration matches the Period Type defined on the Cost Plan Properties page.

To edit the Cost Plan Details TSV cells, change the configuration to reflect the Cost Plan Properties Period Type.

In Clarity Version 13.x, the default configuration for Cost Plan Details TSV is set to use the Cost Plan Properties Period Type.

Here are the Cost Plan Properties and when you change the configuration, the end-user is now able to edit the time-varying cell values:

Clarity Version 12.x

  1. Review the Cost Plan Properties

    <Please see attached file for image>

    Figure 3

  2. Return to the Cost Plan Details page > [--Actions--] Time-Scaled Value > Change Time Scale to 'Year' > Click 'Submit' button

    <Please see attached file for image>

    Figure 4

  3. [--Actions--] Edit Mode -- now the plan is open for editing

    <Please see attached file for image>

    Figure 5

Clarity Version 13.x

  1. Review the Cost Plan Properties

    <Please see attached file for image>

    Figure 6

  2. Return to the Cost Plan Details page > Click 'Options' icon > Time-Scaled Value > Change 'Time Scale' to 'Period Type' > Click 'Save and Return' button

    <Please see attached file for image>

    Figure 7

  3. Return to the Cost Plan Details page > click into a cell and now the plan can be updated using in-line editing

    <Please see attached file for image>

    Figure 8

An Enhancement Request (CLRT-17213) has been proposed, requesting a change in the behavior to allow for end-users to update financial plans with other period types configured on the view.

Keywords: CLARITYKB, how-to, configuration, revmgr.

Environment

Release: ESPCLA99000-12.1-Clarity-Extended Support Plus
Component:

Attachments

1558712422252000049380_sktwi1f5rjvs16sn5.gif get_app
1558712419815000049380_sktwi1f5rjvs16sn4.gif get_app
1558712418027000049380_sktwi1f5rjvs16sn3.gif get_app
1558712416135000049380_sktwi1f5rjvs16sn2.gif get_app
1558712414429000049380_sktwi1f5rjvs16sn1.gif get_app
1558712412540000049380_sktwi1f5rjvs16sn0.gif get_app
1558712410754000049380_sktwi1f5rjvs16smz.gif get_app
1558712408735000049380_sktwi1f5rjvs16smy.gif get_app