Timesheet posting is not correcting the task finish date to match the assignment finish date when there is no remaining ETC (Estimate-To-Completion).
Steps to Reproduce:
Expected Results: The task and summary task finish dates to match the assignment finish date.
Actual Results: The task finish date is not changed and is a week later.
This issue is fixed in CA PPM 13.3.
Workaround:
Edit the assignment and add 1 hour ETC, save, then remove the ETC and save.