Clarity: A project can be deactivated with a Financial Status Open or On Hold

book

Article ID: 49334

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL CA Identity Manager CA Identity Governance CA Identity Portal Clarity PPM SaaS - Application Clarity PPM On Premise

Issue/Introduction

Description:

We set our default Financial Status to 'Hold' or 'Open' and create new projects. Once the project is created, the Project 'Active' attribute field is still editable and an end-user can change the status of the project to 'inactive'. The only valid status to allow a project to become inactive is for the financial status to be 'Closed'.

Steps to Reproduce:

  1. Login to Clarity

  2. Create a new project

  3. Set Financial Status to 'Hold' or 'Open'

  4. Try to change ('uncheck') the project Active attribute

Expected Result: The Project Active field should only be locked when the Financial Status is set to 'Closed'
Actual Result: The Project Active field is locked

Solution:

Workaround:
None.

Status/Resolution:
Resolved in Clarity 12.1.3
Resolved in Clarity 13.1.0

Keywords: CLARITYKB, CLRT-59081, clarity12resolved, clarity1213resolved, clarity13resolved, clarity1310resolved.

Environment

Release: ESPCLA99000-12.1-Clarity-Extended Support Plus
Component: