When exporting a project from Clarity to Microsoft Project (MSP), instead of Assignment Units reflecting allocation set for the resource on the Team tab of the project, they are showing a different value.
Steps to Reproduce:
Expected Results: Units is set to 100 to match the Resource Allocation assigned on the Team tab
Actual Results: Units is set to 50 (pulled from 'Max % Load' for the Assignment)
Applies to the MSP Interface New Driver for all loading patterns and for the MSP Interface Legacy Driver for Uniform Loading Pattern for Clarity 14.2 and higher
This is due to having the "MSP Assignment Units Mapping with PPM Assignment 'Max % Load'" checked in Clarity in Administration->Project Management->Settings
This is working as designed if the "MSP Assignment Units Mapping with PPM Assignment 'Max % Load'" option is checked in Clarity. To disable this setting to have Units in MSP map to the Resource's Allocation on the Team tab: