An event runs Monday - Friday (event A). Another event runs on the 15th of the month (event B) and another runs the last day of the month (event C).
When all three are in the current file the same day I want event B/C both to run before event A. Will event A wait for these?
Release: 5.1
Component: FAQS-Automated Systems Operation
Yes, when all 3 are in the schedule the same day.
Event A will wait for Event B and C. It does not matter which order Event B/C run in.