VCF Operations for Networks 9.1
VCF 9.1
The VCF Operations for Networks Platform appliance failed the upgrade precheck because its allocated storage disk capacity did not meet the mandatory system prerequisite requirements for the configured Extra Large (XL) brick size.
To resolve this, attach an additional 1 TB storage disk to the VCF Operations for Networks Platform VM to meet the prerequisite disk space requirements for the Extra Large (XL) brick size.
Follow the instructions below to increase the disk space on your existing appliance.
Wait 10–15 minutes for VCF Operations for Networks to detect the disk, then verify that the error has disappeared under Settings > Infrastructure and Support. After that, perform the upgrade prechecks again in VCF, and they should complete successfully this time.