Assignment ETC are considered in hours when Unit of Measure is in Days
search cancel

Assignment ETC are considered in hours when Unit of Measure is in Days

book

Article ID: 453390

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

When the Unit of Measure is set to Days, updates to ETC is initially considered in hours. Deleting the ETC values and inputting again, retains and considers the value in Days

STEPS TO REPRODUCE:

  1. Log into Clarity Modern UX and click on the Avatar icon, select Settings option
  2. Click on General tab and select the Unit of Measure as Days
  3. Create a single day duration Task in a project with zero ETC value
  4. Create an single day duration assignment to the above Task by assigning a project resource to it. Note the ETC at the assignment level is Zero by default
  5. Change the Assignment ETC to 1, this shall automatically update the Task ETC similarly

Expected Results :-

The ETC should reflect in days since the Unit of Measure is set to Days

Actual Results :-

The ETC is considered in hours. If the Assignment ETC reset back to zero and then set to 1 day, the ETC is correctly updated to 1 day corresponding with the Unit of Measure

Environment

Clarity 16.4.2, 16.4.3

Cause

DE211039

Resolution

This issue is presently under review by the Engineering Team