Customers using the "Automatic" SLA estimation method may observe that AAI flags jobstreams as having exceeded their deadline almost immediately after a run starts, even if the run completes successfully and on schedule. These alerts may include "Exceeded Deadline," or "Predicted Late,".
Product: Automation Analytics & Intelligence (AAI)
This behavior occurs due to a calculation limitation within the automatic SLA estimation algorithm. When a jobstream is configured to use the automatic SLA method (the system default), AAI estimates the deadline based on historical averages.
Workaround: To resolve this behavior, reconfigure the affected jobstreams to use a deterministic, day-based deadline method instead of the automatic estimation method.
This forces the AAI calculation engine to use the deterministic path, which correctly applies the "never before start" safety guard and prevents the false alerts.
Resolution: This issue has been identified and is scheduled for a permanent fix in AAI release 26.0.