When working with a task set to Fixed Duration in Clarity PPM, reducing the task duration or moving the task start/finish dates can cause the Estimated Time to Complete (ETC) on assigned resources to drop to 0 (zero).
This behavior typically occurs when an assignment is constrained to a specific date range (or a single day) within the original task timeframe, and a subsequent manual change to the task duration or dates shifts the active task window completely outside of the assignment’s scheduled work window.
Steps to Reproduce:
The following table demonstrates how ETC is handled across various date and duration updates on a Fixed Duration task:
| Step | Action | Task Dates | Task Duration | Assignment Start / Finish | Fixed Duration | Loading Pattern | Total ETC | ETC Distribution Behavior |
| 0 | Create Task | Jul 1, 2026 – Jul 31, 2026 | 23 days | — | Yes | — | — | Baseline task created. |
| 1 | Add Assignment | Jul 1, 2026 – Jul 31, 2026 | 23 days | Jul 1, 2026 – Jul 31, 2026 | Yes | Fixed | 184 | ETC is distributed throughout the assignment duration. |
| 2 | Update Task Duration | Jul 1, 2026 – Jul 14, 2026 | 10 days | Jul 1, 2026 – Jul 14, 2026 | Yes | Fixed | 184 | Task finish pulls back; assignment dates update to match the task span. |
| 3 | Update Assignment Start | Jul 1, 2026 – Jul 14, 2026 | 10 days | Jul 6, 2026 – Jul 14, 2026 | Yes | Fixed | 184 | ETC distributes between Jul 6 – Jul 14. |
| 4 | Increase Task Duration | Jul 1, 2026 – Jul 28, 2026 | 20 days | Jul 6, 2026 – Jul 28, 2026 | Yes | Fixed | 184 | ETC distributes between Jul 6 – Jul 28. |
| 5 | Shift Assignment Start | Jul 1, 2026 – Jul 28, 2026 | 20 days | Jul 27, 2026 – Jul 28, 2026 | Yes | Fixed | 184 | ETC distributes between Jul 27 – Jul 28. |
| 6 | Reduce Task Duration | Jul 1, 2026 – Jul 14, 2026 | 10 days | NULL / NULL | Yes | Fixed | 0 | ETC becomes 0. Task finish moves to Jul 14, cutting off the assignment start (Jul 27). Assignment window is outside task boundaries. |
Clarity 16.4.2
This behavior is Working as Designed.
Workaround:
Use one of the following methods:
Manually re-enter the desired ETC values on the assignment within the new active task date range.
If no actuals have been posted against the task assignment, delete and re-add the assignment so Clarity automatically distributes the ETC across the newly defined task span.
If scheduling flexibility is required when changing task durations:
Disable the Fixed Duration setting prior to editing dates/durations if you wish the task dates to dynamically adapt to assignment ETC.
Ensure task duration and task date range adjustments are finalized before locking assignments to specific single-day or constrained timeframes.