When navigating to the Tasks tab (Gantt/Timeline view) of a master project, right-clicking a regular summary task displays the Expand All option in the context menu. However, when right-clicking a row corresponding to an added subproject, the Expand All option is missing.
Clarity All Supported Version
A subproject entry within a master project's Tasks/Gantt view functions as a proxy link pointing to an independent project record. It does not physically embed or store the child project's task structure inside the master project's local hierarchy.
Because the subproject's task structure is owned and loaded from the subproject itself, actions that require recursively loading, linking, or duplicating child tasks are restricted from the master project's context menu:
Actions that manage only the link itself (such as Open Details, Collapse All, Insert Sibling, Insert Child, and Delete) remain available.
This behavior is by design
To expand and manage the full task hierarchy of a subproject, open the subproject directly:
Note: This design standard applies across Clarity's Work Breakdown Structure (WBS) management. Structural task operations—including Indent, Outdent, Move, and Baseline Updates—are similarly restricted on subproject proxy nodes because task ownership resides exclusively within the subproject itself.