Allocation hours for Material type in DWH are missing.
search cancel

Allocation hours for Material type in DWH are missing.

book

Article ID: 450124

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

You are observing that for the Material resource type allocation hours are not populated in DWH_INV_TEAM_PER_FACTS_M_V.

Steps to Reproduce:

  1. Create a financially enabled project.
  2. Add four staff members to the project team, one of each: a named Labor resource, a Role, an Equipment resource (type "Hardware"), and a Material resource.
  3. Ensure the project's Transaction Matrix has Rate Source and Cost Source configured for all four resource types (Labor Matrix + non-labor Matrix segments for Equipment and Material).
  4. Run Rate Matrix Extraction job (Prepare + Update, full).
  5. Give each of the four team members an allocation (hours/units) on the Team page.
  6. Run Update Cost Totals on the project.
  7. Confirm in Clarity UI (Staff/Team page) that all four resources show both Allocation and Allocation Cost.
  8. Run the Time Slicing job(s).
  9. Run Load Data Warehouse (Full).

Expected Results: alloc_hours are populated in DWH_INV_TEAM_PER_FACTS_V for Material type.

Actual Results: alloc_hours are NOT populated in DWH_INV_TEAM_PER_FACTS_V for Material type.

Environment

Clarity 16.4.x

Cause

DE209818

Resolution

Fixed in 16.5.0.