When a new project is created from a project template ("New Project from Template") and the new project's start date differs from the template's own task dates, task Start/Finish/Duration and assignment dates shift inconsistently depending on whether the task carries ETC on its assignment and whether it is marked Fixed Duration. Only tasks with no ETC + Fixed Duration = Yes shift correctly. Tasks with ETC end up with dates/durations pinned (fully or partially) to the template's original absolute values instead of shifting relative to the new project's start
Preconditions
Steps to Reproduce:
Expected Results: All three tasks — regardless of ETC or Fixed Duration setting — shift by the same workday offset relative to the new project's Start date, and each task's original Duration is preserved. Assignment Start/Finish move with their tasks.
Actual Results: The new project's start date (Jul 31, 2026) is about 4 months earlier than the template's task dates (Dec 3-16, 2026). All 3 tasks should have shifted back by that same 4-month gap and kept their 10-day length. Only TEST 2 (no ETC) did that correctly. Any task with ETC on its assignment (TEST 1, TEST 3) got its dates handled wrong
| Task | ETC | Fixed Duration | Template Start | Template Finish | Template Duration | New Project Start | New Project Finish | New Project Duration | Notes |
| TEST 3 | 15 | Yes | Dec 3, 2026 | Dec 16, 2026 | 10 | Jul 31, 2026 | Dec 16, 2026 | 99 | Only half moved - Start date shifted correctly, but Finish date was left on the template's original date, so the task now looks like it spans ~5 months instead of 10 days. |
| TEST 2 | 0 | Yes | Dec 3, 2026 | Dec 16, 2026 | 10 | Jul 31, 2026 | Aug 13, 2026 | 10 | Worked correctly - shifted back by the same gap as the new project's start date and kept its original 10-day length. |
| TEST 1 | 15 | No | Dec 3, 2026 | Dec 16, 2026 | 10 | Dec 3, 2026 | Dec 16, 2026 | 10 | Didn't move at all - still sitting on the same dates as the template, as if the new project's start date was never applied. |
Clarity 16.3.3, 16.4.0,16.4.1,16.4.2
DE209846
DE209846, in review by Engineering
Workaround: After creating a project from a template whose start date differs from the template's own dates, manually review and correct Start/Finish dates (and assignment dates) on any task that has ETC