While upgrading vCenter Server from 8.0u3 to 9.1, the Stage 2 pre-check fails. The user may see errors regarding incompatible Host Profiles or Distributed Switches. In some instances, the deployment wizard may prompt for credentials that fail to authenticate, even if the credentials are valid for SSH.
Symptoms:
vCenter Server 8.0u3 (Source)
vCenter Server 9.1 (Target)
VMware Cloud Foundation 9.x
The upgrade pre-check identifies legacy Host Profile metadata that does not meet the schema requirements for vCenter 9.1. The authentication failure typically occurs when the upgrade wizard enters a transient state following a failed validation check.
If the issue persists with Distributed Switches, ensure all switches are upgraded to a version compatible with the source vCenter before attempting the 9.1 upgrade.