The subproject task dates are incorrect when autoscheduling a subproject that is locked.
search cancel

The subproject task dates are incorrect when autoscheduling a subproject that is locked.

book

Article ID: 444369

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

The subproject task dates are incorrect in the main project when autoscheduling while a subproject is locked.

Steps to Reproduce: 

  1. Create a main project and subproject
  2. Add tasks to both with 30 days duration
  3. In the timeline view click AutoSchedule
  4. In a new browser tab, go to the the main project
  5. In timeline view, click actions>>Autoschedule
  6. Discard the tentative schedule in the child project
  7. publish the autoschedule in the main project

 

Expected Results: The subproject task dates will return to the original dates since the schedule was not published

Actual Results: The subproject task dates are published as they were in the tentative schedule, however the summary task dates are correct.

Environment

Clarity 16.4.1+

Cause

DE204985

Resolution

Submitted to engineering for analysis