Tasks workspace Timeline view: Filtering on Assigned Resources
search cancel

Tasks workspace Timeline view: Filtering on Assigned Resources

book

Article ID: 444044

calendar_today

Updated On:

Products

Clarity FedRAMP Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

The Assigned Resources filter on the Tasks workspace timeline displays every task of the project where the resource has got assignments, regardless of being assigned or not.

STEPS TO REPRODUCE:

  1. Create a project Project1
  2. Assign Res1
  3. Create 2 tasks and assign the Resource to only 1 of them
  4. Go to MUX > Tasks workspace > Timeline view
  5. Add the Assigned Resources field to the filter and add Res1 to it
  6. Project1 is returned by the filter. Expand the project

Expected Results: Only the task where the resource is assigned is visible
Actual Results: Both tasks are visible, also the one where the resource is not assigned 

Environment

Clarity 16.4.2

Cause

This is caused by DE204563

Resolution

This is fixed in Clarity 16.4.3

Additional Information

A similar defect was fixed in 16.4.0