The Assigned Resources filter on the Tasks workspace timeline displays every task of the project where the resource has got assignments, regardless of being assigned or not.
STEPS TO REPRODUCE:
Expected Results: Only the task where the resource is assigned is visible
Actual Results: Both tasks are visible, also the one where the resource is not assigned
Clarity 16.4.2
This is caused by DE204563
This is fixed in Clarity 16.4.3
A similar defect was fixed in 16.4.0