Issue/Introduction

We are likely to monitor 4 parameters in cdm probe but here we don't want that it should collect the data for every 5 min we want it for 24hr is it possible is there any possibilities.

Environment

UIM 23.4.6

CDM 8.08

Resolution

You can define a schedule that enables you to run the profile on specific date and time. Use this option if you do NOT want to use the interval time (as specified in the Setup tab -> Control Properties tab). For example, run the profile to monitor only on Wednesday mornings at 8:00 A.M.


Follow these steps:


= In the Setup  window, click the Schedulestab.


= Right-click and select Add. The New Schedule dialog opens.


     == Specify a name for the schedule.


     == Specify the start and end of the schedule in the Range  section.


     == Specify the frequency of the schedule.


     == Specify whether to generate alarms or QoS only for a day or within a time  frame on specific days.


     == Click OK . The schedule is created.