When an Assignment's ETC is updated within the Details pane, the Task's Per-Period Metrics do not automatically update to reflect the new values.
Steps to Reproduce:
Log in to Clarity.
Navigate to the Task Workspace (Note: This behavior is also present in the Tasks Module of a Project).
Configure the ETC as a Per-Period Metric using Monthly periods for the current year.
Select a Task that ends on a specific date (e.g., October 31, 2026) and has resources assigned to it.
Open the Details pane and configure the ETC Per-Period Metric with Monthly periods for the current year.
Modify the ETC of the assigned resource for a specific month (e.g., June 2026) to a new value.
Close the Details pane.
Expected Result: The ETC is updated correctly on the Task's Per-Period Metrics.
Actual Result: The Task ETC remains unchanged and is not updated.
Clarity PPM 16.x
DE196265
Issue DE196265 is under Engineering Review