Task ETCs Do Not Update When Assignment ETCs Are Modified
search cancel

Task ETCs Do Not Update When Assignment ETCs Are Modified

book

Article ID: 440777

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

When an Assignment's ETC is updated within the Details pane, the Task's Per-Period Metrics do not automatically update to reflect the new values.

Steps to Reproduce:

  1. Log in to Clarity.

  2. Navigate to the Task Workspace (Note: This behavior is also present in the Tasks Module of a Project).

  3. Configure the ETC as a Per-Period Metric using Monthly periods for the current year.

  4. Select a Task that ends on a specific date (e.g., October 31, 2026) and has resources assigned to it.

  5. Open the Details pane and configure the ETC Per-Period Metric with Monthly periods for the current year.

  6. Modify the ETC of the assigned resource for a specific month (e.g., June 2026) to a new value.

  7. Close the Details pane.

Expected Result: The ETC is updated correctly on the Task's Per-Period Metrics.

Actual Result: The Task ETC remains unchanged and is not updated.

Environment

Clarity PPM 16.x

Cause

DE196265

Resolution

Issue DE196265 is under Engineering Review