Update % Complete job performance with Milestones selected
search cancel

Update % Complete job performance with Milestones selected

book

Article ID: 437480

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

When a large customer runs the job with no restrictions and simply with the Milestones checkbox enabled, the job will take 5 minutes to complete

STEPS TO REPRODUCE:

  1. On a large customer system with 2K active projects, go to Jobs
  2. Select Update % Complete
  3. Do not fill any of the parameters, leave them empty
  4. Just check Include Milestones when Updating Task Status to be enabled
  5. Run the job

Expected Results: the job to complete within reasonable amount of time

Actual Results: The jobs runs for 5+ Minutes for 2K projects

Workaround: None

Environment

Clarity 16.4.1

Cause

DE187432

Resolution

In review by Engineering

Workaround: Run the job without Milestones selected throughout the day, run the Milestones once daily