Checklists, Tasks, and To-Dos Not Copying from Specific Project Templates
search cancel

Checklists, Tasks, and To-Dos Not Copying from Specific Project Templates

book

Article ID: 437035

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

When creating a new project from a specific project template, the checklists, tasks, and to-dos are not copied to the new project.

  • Other project templates in the same environment may work correctly.
  • The issue persists even if linked processes are placed on hold

 

Environment

All Supported Versions

Resolution

Perform a direct copy of the problematic project template and use the new copy as the template for future projects.