Issue/Introduction

A user is unable to see or add specific tasks to their timesheet using the Add Tasks option, despite the project being active, the user being assigned to the tasks, and the tasks having remaining ETC and "In Progress" status. Here is a summary of validation step performed. 

 

Category Validation Step Performed Status
Project Verified Project is Active ✅ Complete
Project Confirmed other tasks are visible in the user's timesheet ✅ Complete
Task Verified Task Status is "Started" (In Progress) ✅ Complete
Task Verified Task "Open for Time Entry" (OTE) is Enabled ✅ Complete
Task Confirmed affected Tasks are parent tasks (So it is not like OTE needs to be enabled on the parent task) ✅ Complete
Task Verified Task Dates (Jan 1 – Mar 31) cover the Feb period ✅ Complete
Staffing Verified Resource is included in the Project Staff ✅ Complete
Assignment Verified Resource is explicitly assigned to the task ✅ Complete
Assignment Confirmed Assignment ETC is greater than 0 ✅ Complete
Historical Confirmed task was available for entry in previous months ✅ Complete

Environment

Clarity 16.4.1

Resolution

The issue is caused by the Open for Time Entry (OTE) flag being disabled at the Staff (Team) level. In Clarity 16.0 onwards, the "Chain of OTE" must be fully intact across all levels.

To resolve, ensure the following configuration:

 

Level Parameter Required Value Location in UI
Project Track Mode PPM Project > Properties > Settings
Project Open for Time Entry True Project > Properties > Settings
Resource Track Mode PPM Resource > Properties
Resource Open for Time Entry True (Checked) Resource > Properties
Staff (Team) Open for Time Entry True (Checked) Project > Team [Staff View]
Task Open for Time Entry True (Checked) Task > Properties
Assignment Open for Time Entry True (Checked) Task > Assignments

Additional Information

Please refer to KB Timesheet Population - What Determines Tasks To Display on a Timesheet?

There is spreadsheet attached at the bottom of this article for more info on outcome in Modern UX Timesheets 'Add Assigned Tasks' or 'Select Tasks' actions.