Import Financial Actuals Creates Assignment on Milestone Task
search cancel

Import Financial Actuals Creates Assignment on Milestone Task

book

Article ID: 432417

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS Clarity FedRAMP

Issue/Introduction

When a transaction is posted against a task and that task is subsequently converted to a milestone before the Import Financial Actuals job runs, the job processes the transaction without error and creates a PRASSIGNMENT record on the milestone task. This leaves the project in an inconsistent state — a milestone task that carries an assignment — which is a state the system explicitly prevents through normal project planning flows.

Steps to Reproduce

  1. Create a task that is not a milestone (PRTASK.PRISMILESTONE = 0) and has no assignments (PRASSIGNMENT).
  2. Post a financial transaction for this task into IMP_TRANSACTIONIMPORT (e.g. via the Transaction Entry portlet or XOG).
  3. Before running the job, mark the task as a milestone (PRTASK.PRISMILESTONE = 1). The UI allows this.
  4. Run Import Financial Actuals job

Expected Result: Job will error saying the task is a milestone and cannot have assignments.

Actual Result: The job succeeds, and the task is now a milestone with an assignment — an invalid, inconsistent data state.

Environment

Clarity 16.4.0, 16.4.1

Cause

DE183676

Resolution

Fixed in 

  • Clarity 16.4.2