When running "Populate from Allocations" on a Cost Plan, a Named Resource picks up a rate based on their personal Financial Location rather than the Project Location. This happens even when the Financial Management WIP Settings are explicitly configured to source the "Project Location". At the same time, generic Roles correctly default to the Project Location rate.
Clarity PPM On Premise, Clarity PPM SaaS
Clarity separates the logic for Actuals (WIP) and Planning (Cost Plans). Financial Management WIP Settings only control the default values for posted transactions (Actuals).
The Cost Plan "Populate from Allocations" action bypasses WIP Settings entirely. Instead, it is governed by the Entity's Plan Defaults. If the Entity's Labor Rate and Cost Defaults are configured to use the "Resource", the system is strictly instructed at the Entity level to prioritize the Resource's personal location over the Project's location when reading the Rate Matrix.
To force the Cost Plan to respect the Project Location and align the estimates with your WIP settings, you must update the Entity Plan Defaults.