Update Per-Period Metrics ETC in Scenario
search cancel

Update Per-Period Metrics ETC in Scenario

book

Article ID: 430079

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

In MUX, scenarios can be used to update Allocations in the Per Period Metrics, however it is not possible to do the same with ETC.  Will that be available in the future?

Resolution

There are no plans to include the ability to update per-period metrics ETC when in a scenario.

This functionality was never available in Classic Clarity either.