Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

  • Update Investment Allocation and Usage Job is stuck
  • It is causing long running sessions in the Clarity DB
  • It is also causing blocking sessions
  • Multiple time entry locks are also noticed.

Cause

  • The job is not the cause but a victim of a massive data change in the system
  • The data change is concentrated on the prtimesheet and prassignment tables
  • The job relies on prassignment table, amongst others, to get its data
  • It updates only inv_investments table.

Resolution

  • It is best to do data loads during non-working hours of a Production system.