The earliest start time set on the start task of workflows is not taken into account in the calculation of schedule simulations, which gives inconsistent forecast results.
Steps to reproduce:
- Create a workflow
- Add a task between the start and end of this workflow.
- Set earliest start time to start object
- Create a forecast of this jobplan
Automation Engine v24.4.3 and v24.4.2
DE180725
A problem has been fixed that prevents displaying proper forecast results.
Update to a fix version listed below or a newer version if available.
Fix version:
Component(s): Automation Engine
Automation.Engine 24.4.4 - Planned release March 2026