This KB article details the mandatory pre-execution checks and operational procedures required before initiating a Test Recovery, Planned Migration, or Disaster Recovery (DR) plan in VMware Live Recovery / Site Recovery Manager (SRM).
VMware Live Recovery 9.x
Follow the two-phase validation and execution process outlined below to ensure a smooth recovery operation and prevent VMware Live Recovery workflow failures.
Phase 1: Pre-Execution Health Checklist
Perform and verify all of the following checks in the SRM / VMware Live Recovery interface prior to triggering any recovery workflow:
Phase 2: Test Recovery | Disaster Recovery Execution Procedure
Initiate the Test / Disaster Recovery Plan based on the requirement:
Access the recovery site SRM appliance management interface at: https://<Recovery_SRM_IP>/dr
Select the target Recovery Plan.
Click Run and choose the Disaster Recovery option.
Post-Failover Cleanup:
Once virtual machines are successfully powered on and verified at the recovery site, remove any active site isolation configurations.
Execute Reprotect Workflow:
After network communication and site pairing are fully restored between both sites, execute the Reprotect command in SRM.
This step reverses the replication direction and creates placeholder VMs at the original primary site for future failback operations.
Note : Running a recovery plan while SRA devices are in an In Progress or Unknown state can lead to storage mounting failures and inconsistent datastore states at the recovery site. Always wait for device discovery to complete fully before proceeding.