The Next Scheduled Time is blank. The schedule has:
Last workday of month less 4 workdays
When trying to Simulate the event, it works.
ESP dSeries / Workload Automation DE: 12.3 or above
If only one (1) day, then workdays won't work. e.g. For just one day, this should work:
Last workday of month less 1 workday
For more than one day, this will work:
Last workday of month less 4 workdays
https://techdocs.broadcom.com/us/en/ca-enterprise-software/intelligent-automation/ca-workload-automation-de/12-4/scheduling/examples-cookbook/scheduling-a-job-to-run-on-the-last-five-workdays-of-the-month.html