Non-clickable Area around "Today" overlaps with (should be clickable) Task Timeline View
search cancel

Non-clickable Area around "Today" overlaps with (should be clickable) Task Timeline View

book

Article ID: 424073

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity FedRAMP Clarity PPM SaaS

Issue/Introduction

The non-clickable area of the Star overlaps with the task for the 1st task making the duration not draggable. 

Steps to Reproduce: 

  1. Login to Clarity MUX Using Project Management rights
  2. Navigate to  MUX Project Workspace and go to the task tab
  3. Open the timeline view pf the task
  4. Click on View Options and enable "Show today" toggle
  5. Create a new Task, add the phase but don't change the date
  6. Task will be created in the first line of the view with a small duration probably with single day

Expected Results: The length of the task can be changed by moving the mouse anywhere on the side of the task line, mouse changes into an arrow and length of task can be changed.

Actual Results: The non-clickable area of the Star overlaps with the task. The arrow only appears in a very small area at the bottom of the task.

Environment

Clarity 16.3.3, 16.4.0,16.4.1

Cause

DE180727

Resolution

Workaround: Update the start and finish date of the particular task using the grid or the Details Flyout panel.

Fixed in

  • Clarity 16.4.2