Update Cost Totals action in MUX
search cancel

Update Cost Totals action in MUX

book

Article ID: 423097

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

In Classic UI when going to the Project Tasks tab we can see the Update Cost Totals action. In MUX though this is not available. Is there any configuration that can be done to get the same action in MUX?

Environment

Clarity 16.2.3 and higher

Resolution

In Clarity 16.2.3, the Update Cost Totals action has been introduced in MUX:

  • This is available in the Tasks Timeline layout only
  • This is governed by access rights: Project - Update Cost Totals
  • This will give the ability to Update Cost totals for the entire Investment