In Classic UI when going to the Project Tasks tab we can see the Update Cost Totals action. In MUX though this is not available. Is there any configuration that can be done to get the same action in MUX?
Clarity 16.2.3 and higher
In Clarity 16.2.3, the Update Cost Totals action has been introduced in MUX: