Issue/Introduction

Question: 

The usage of split tasks and recurring tasks in MS Project can be submited to CA PPM?

Environment:  

CA PPM v13.x, CA PPM v14.x

Answer: 

CA PPM does not support both the split task functionality as recurring task of Microsoft Project.

 

Environment

Release: ESPCLA99000-13.2-Clarity-Extended Support Plus