During VMware HCX Bulk Migration, the migration task remains stuck in the Initial Sync phase. No data replication begins, and the migration does not progress even after multiple retries.
User may observe:
HCX
The Transfer Schedule window configured for the Bulk Migration is too short to allow HCX to initiate the base synchronization.
HCX relies on the defined Transfer Schedule to determine when it is permitted to start the Initial Sync. If the allowed time window is too narrow:
Increase the Transfer Schedule duration to provide HCX with sufficient time to start and complete the Initial Sync.
Steps to Resolve
Once the schedule window is expanded, HCX will initiate the Initial Sync successfully, and replication will proceed as expected.