Rally SaaS

Issue/Introduction

A User trying to update 'Time Spent' and 'Task Estimate' on the Rally iteration Dashboard, but user is unable to edit these fields.

These fields seem to be locked or non-responsive when user click on them.

Environment

Rally SAAS

Cause

Working as designed

Resolution

The 'Time Spent' and 'Task Estimate' fields on the Rally Iteration Dashboard are system-generated and automatically calculated. Their values are derived from the plan estimates set for tasks within a user story and finalize upon task completion.

These fields are not directly editable by users, manual adjustments are not possible. To influence these values, Users must modify the underlying 'Plan Estimates' of the individual tasks.