ConnectAll Orphan management not running due to "Unexpected error occurred in scheduled task" error
search cancel

ConnectAll Orphan management not running due to "Unexpected error occurred in scheduled task" error

book

Article ID: 419231

calendar_today

Updated On:

Products

ConnectAll On-Prem ConnectALL

Issue/Introduction

Several orphan management plans were scheduled to run daily, but items were not being cleaned up via orphan management.   

We see the following error in the Orphan log: Unexpected error occurred in scheduled task

Found in Release 3.9.1

 

Steps to Reproduce: 

  1. Set up Orphan Management job

Expected Results: 

  • The job runs at the expected time

Actual Results:

  • The job doesn't run at all

Workaround: 

  • Start the Orphan job manually.

 

Environment

On Premise.

Cause

DE178520

Resolution

Fixed in release 4.0.1 patch.