When opening a project in the Microsoft Project (MSP) New Driver, task durations are exported incorrectly if the base calendar is not set to 8 hour per day shifts.
Steps to Reproduce:
Expected Result: Task has a 1 day duration matching PPM
Actual Result: Task has a duration of 1.07, finishing at 9AM the following day
This issue is caused by CLRT-79717/DE33790
This issue as been fixed CA PPM 15.1 patch 6, 15.2 patch 3, and 15.3.
Workaround:
1. Adjust the task duration to match that of CA PPM before saving from MSP
OR
2. Add a dummy assignment to any tasks without assignments
OR
3. Use the MSP Legacy Driver
Reference the Customer Reported Defect Resolution Policy for CA PPM