The CAJUTIL0 command REPORT COMPLETE JOB=jobname,SCHEDULE=schedname,SDATE=091821,FOR=1
produces report for 09/18/21 and 09/19/21. The user expects to see a completed job report for 09/18/21 only. Parameter FOR=1 is not honored.
Use FROMDATE.
Example: REPORT COMPLETE JOB=jobname,SCHEDULE=schedname,FROMDATE=091821
produces Job Complete report for 9/18/21.