Question:
We need to update Actuals time in Assignments via Open Workbench instead of Clarity Timesheet.
How do I configure PPM and Open Workbench?
Environment:
PPM Clarity 13.x, 14.2
Answer:
Need to configure Track Mode=None for both Project and Resources as below.
- For project
<Please see attached file for image>
- For Resource
<Please see attached file for image>
After above configurations, you can use Status Update view in Open Workbench to update Actuals for each resources like as below.
<Please see attached file for image>
After save this project to PPM(total 36 hours Actuals) , you will see 36 hours Actuals of Assignment in PPM.
<Please see attached file for image>
Additional Information:
If you want to update Actuals by using MS Project, you can use similar configuration.